Coal mining subsidence area 1GW photovoltaic project in Yangquan

In January, 2017, CYG won the bid of the project and become the overall secondary contractor for the project, who was responsible for the complete secondary system integration of two 220kV, eight 110kV booster stations and multiple PV power plants. CYG have to provide 27 large-scale secondary containers, 600+ equipment panels, 1,000+ units of equipment for this project.

SinceFebruary 6th CYG formallysigned the business contract→March 16th started thecontainerassemblywork→April 21th completed the factory shipments,totallyshared 75 days, of whichtheassembly work time of containers lasted37 days.