On November 27, 2025, the 10 kV live-upgrade project for Deqing Station at 35 kV Duilong in Lhasa, Xizang, undertaken by CHENGDU QICHENG ELECTRIC POWER CO., LTD. (CYG Qicheng), a wholly-owned subsidiary of CYG SUNRI, was successfully put into operation.
As the first successful application of CYG SUNRI’s portable live-upgrade platform in Xizang, this project marks that the company has established a complete substation technical upgrade system covering plateau and other scenarios to meet diversified demands.
First Success of Live-Upgrade on the Plateau, Premiere of Portable Solution
Under the leadership of the dispatching department of Lhasa Power Supply Company, CYG Qicheng gave full play to its technical advantages and used the portable live-upgrade platform jointly developed with CYG SUNRI to complete the bay upgrade of three 10 kV feeders at Deqing Station under full live-line conditions, with only short-time power outage for verification at the final stage. This has maximized the continuity and reliability of local power supply for people’s livelihood.
Adopting a modular and prefabricated platform, the solution supports on-site plug-and-play and rapid deployment.
The portable design and intelligent technology reduce operation difficulty and adapt to complex environments.
No power outage is required for primary equipment during the upgrade, ensuring continuous and reliable power supply for important user loads to the greatest extent.

▲ CYG SUNRI 300G-KP Portable Live-Upgrade Platform
The solution is especially suitable for the upgrade of 10 kV feeder protection and measurement & control devices. By configuring temporary protection, seamless signal switching and real-time monitoring, it achieves the goal of “no power outage for primary equipment and no loss of protection functions during upgrade”. It performs stably even in complex plateau environments, verifying the maturity and reliability of the solution.

▲ On-site personnel carrying out live-upgrade work
Beyond “Live-Upgrade”: Three Core Upgrade Solutions Covering Full Scenarios
Based on rich on-site practices and technical accumulation, the company has developed three core solutions: Rapid Upgrade, Live-Upgrade and Overall Upgrade, which can provide customized services for different voltage levels, upgrade demands and construction conditions.
// Rapid Upgrade Solution
Mainly for single-bay upgrades of 220 kV and above. Through detailed preliminary survey, prefabricated wiring in the factory and standardized drawing design, the solution greatly shortens on-site construction and power outage time, realizing rapid implementation featuring “safety, reliability and cost effectiveness”.
► The solution has been successfully applied in many provinces and cities including Zhejiang, Shanghai and Henan, winning wide recognition from customers for its remarkable efficiency advantages.
// Live-Upgrade Solution
Focusing on the upgrade of 10 kV feeder protection and measurement & control devices, the solution adopts technologies including temporary protection access, intelligent circuit switching and full-process monitoring to complete equipment upgrade without affecting power supply. It is especially suitable for civil and industrial load areas with high requirements for power supply continuity.
► The solution has been applied not only in this plateau project in Xizang, but also successfully implemented many times in Gansu, Ningxia, Shanxi and other regions.
// Overall Upgrade Solution
Provides EPC general contracting or professional subcontracting services covering design, supply, construction and commissioning, to meet the comprehensive technical renovation demands of the whole substation. Through a professional team and systematic management, it achieves unified resource coordination, safe and controllable implementation and improved efficiency, suitable for overall substation upgrade or large-scale renovation projects.
► The company has successfully delivered a number of major projects in this field, including the EPC general contracting of 220 kV Longyuan Substation in Liaoning, 110 kV Ciba Substation in Kunming, Yunnan and 110 kV Yangqing Substation in Zhongshan, Guangdong, which fully verify its strong strength in whole-station technical renovation and engineering general contracting.
CYG Qicheng has always adhered to creating engineering practice value with technical expertise. It possesses a number of qualifications, including Second-Class General Contracting for Electric Power Engineering, Second-Class Certification for Power Installation, Repair & Test, Second-Class Specialized Contracting for Construction Mechanical and Electrical Installation Engineering, Unclassified Construction Labor Service and Safety Production License. Adhering to lean construction and intelligent operation & maintenance, it has won wide recognition and trust from the market.
Moving forward, CYG SUNRI and CYG Qicheng will continue to deepen technical R&D and solution optimization, expand the application scope of the three technical renovation modes: "Rapid Upgrade, Live-Upgrade and Overall Upgrade", and join hands with industrial partners to promote the development of power grids towards a safer, smarter and more efficient direction, providing solid support for the digital transformation and reliable operation of China's power system.